How do I configure a Phoenix Contact EEM-MA371 kWh meter for the energy controller?

This manual is designed for installers with experience using this meter. Maxem uses the energy controller and the Energy Cloud to read the kWh meter and receive readings from, for example, the main connection to this kWh meter.

Installation Preparation

Proper preparation is essential for a smooth installation. Carefully follow the guidelines below to ensure the installation and configuration process runs without issues.
A small flat-head or Phillips screwdriver is required for installation.

Without proper configuration of the Phoenix Contact EEM-MA371 kWh meter, Maxem cannot perform Dynamic Load Management (DLM) if this kWh meter is measuring the main connection.

Requirements

Before you can configure the Phoenix Contact EEM-MA371 kWh meter, the following conditions must be met:

  • The kWh meter has been physically installed correctly.

  • The Maxem Energy Controller has been successfully installed and is operational.

Only when both components are fully functional can the kWh meter be configured for communication with the Maxem Energy Controller.

Installation Steps

This section provides a step-by-step guide on how to configure the Phoenix Contact EEM-MA371 kWh meter.
Images or visual aids may be added to support these instructions if necessary.

For Connections Using Rogowski Coils

The following instructions are specific to installations using Rogowski coils.

Display and Button Overview

The Phoenix Contact EEM-MA371 is operated using four buttons (1–4).
The display shows icons indicating which action is available.
Press the button corresponding to the displayed icon to execute the desired action.

Icon Overview

 

Configuring the Phoenix Contact EEM-MA371 kWh Meter

The configuration consists of two main steps.

Step 1: Configure the Measurement System

  1. Press any button to activate the display.

  2. Press Button 4 (☰) to open the Settings menu.

  3. Use Button 2 (↓) to navigate to the Measurement System menu.

  4. Press Button 3 (→) to open this menu.

  5. Press Button 3 (EDIT) to select the correct setting for Grid Type.

  6. Use Button 2 (↓) to navigate to Current Input.

  7. Press Button 3 (EDIT) and configure the correct value based on the Rogowski coils in use.

  8. Ensure that all other settings within this menu remain unchanged.

  9. Press Button 3 (OK) to save the configuration.

  10. When prompted with “Keep changes?”, confirm by pressing Button 1 (✓).

 

Step 2: Configure Ethernet Settings

  1. Activate the display (press any button).

  2. Press Button 4 (☰) to open the Settings menu.

  3. Use Button 2 (↓) to navigate to Network.

  4. Press Button 3 (→) to open the Network menu.

  5. Confirm that you wish to modify the network settings (Button 1 →).

  6. Select IPv4 (Button 3 →).

  7. The meter displays the default IP address 192.168.1.2 for Mode.
    Press Button 4 (EDIT) to change this to one of the following:

    Meter IP Address
    1st meter 192.168.25.10
    2nd meter 192.168.25.11
    3rd meter 192.168.25.12
    etc.

    Button functions while editing:

    • Button 1 (+): Increase value

    • Button 2 (→): Move to the next position

    • Button 3 (OK): Confirm value

  8. Subnet mask: Leave unchanged (255.255.255.0).

  9. Navigate to Standard Gateway → set to 192.168.25.1 using EDIT.

  10. DNS server: Leave unchanged (0.0.0.0).

  11. Press Button 3 (OK) to save settings.

  12. When prompted with “Keep changes?”, confirm by pressing Button 1 (✓).

  13. The default settings for Modbus TCP remain active:

    • Unit ID: 3

    • Port number: 502

  14. Within the Network menu, navigate to Modbus comp. active and enable the checkbox to ensure the correct byte order is used for communication.

  15. Press Button 3 (OK) to save settings.

  16. When prompted with “Keep changes?”, confirm by pressing Button 1 (✓).

 

Configuration and Testing

After configuration, verify that the Maxem Energy Controller successfully communicates with the Phoenix Contact EEM-MA371 kWh meter.

Test Procedure

  1. Check whether the kWh meter is visible within the Energy Controller.

  2. If communication is unsuccessful:

    • Repeat Section 5: Installation Steps.

    • Verify all IP and network settings.

    • Check the wiring and power supply of the meter.

When communication is successfully established, the installation of the Phoenix Contact EEM-MA371 kWh meter is complete.

 

Tip: Always document the assigned IP address and Unit ID of each meter for future maintenance or troubleshooting purposes.

 

Instructions from the manufacturer